SEABEESSEABEE LOGOsmaller.jpg (35768 bytes)

     Naval Mobile Construction Battalion 71

Home ]

the veteran 3 (10628 bytes)

SeaBeeRight.jpg (70966 bytes)

 

Building the Dome

New South Pole 1973

This material is from Southpolestation.Com

The photos are still linked there - when you click you'll get a larger photo from that site.


digging the Pole
Preliminary site prep began during the 1970-71 season, as you see here (right) a Peter Snow Miller is doing well at processing the dome and utilidor foundations. Unfortunately, these machines couldn't handle the Pole altitude and snow conditions over the long term, and much of the foundations were compacted by running the D8's over them. photo from Gary Brougham


ring around the Pole
Here is a view of the early construction of the dome base ring from the 1971-72 season (Navy photo, Antarctic Journal (AJ) 3/72). The dome snow foundation was complete on 19 January, and by the 22nd the base ring erection had begun. Very little of the ring actually got built during the first season. However, 80% of the 720' utilidor was completed.



all it's cracked up to be?

This diagram from the TEMCOR dome erection manual shows the details of the foundation base ring. The differential settlement of the timber pads underneath this foundation caused some of the aluminum nodes and base ring beams to break eventually, these were repaired in 1989-90.


dig deep

The photo at left (this and the next 2 photos courtesy Bob Nyden from a 72-73 cruisebook) shows early construction of the dome ring, while excavation for the utilidor is also proceeding.


skeletons

The lower portion of the ring is mostly in place


pump it up!!
Seabees assemble the lower portions of the dome.



this is a stick up
Erection of the dome required scaffold towers around the edges to support the lower portion of the dome ring until the entire geodesic structure was completed. The central portion was erected on the surface, and slowly raised on a central scaffold tower. At left you see the tower being erected (Navy photo, AJ 7/73)


REALLY pump it up!
This page from the TEMCOR manual shows the central tower and the initial assembly of the upper portion of the dome. The 5-legged tower had 10 winches which attached to the upper portion, after each ring was added the assembly was pulled up and the next ring installed.



towering over Pole
This view from outside the dome shows the central tower supporting the skeleton of the upper portion of the dome, behind the lower portion which has some of the skin panels installed. (this and the next photo from NSF courtesy Jerry Marty)


towering over the pole
At left, a closer view of the tower, as the raising of the central portion of the dome is underway.



Bucky Fuller would have been proud
At right, later in the season (Navy photo, AJ 7/73) the dome upper portion assembly has been completed, with its outer edge resting on the snow surface. Here the central tower is being dismantled; portions of it will be erected at 10 equally spaced points around the edges of the upper section, to lift it up to join the lower portion of the dome ring, which is visible in the background.



roofing
This page from the TEMCOR manual shows how the sheet aluminum dome panels are installed. As you can see, removing the panels is rather difficult (as we found out in 1989-90; also all of the fasteners which connect the nodes (circular pieces) to the beams, are "Huck" fasteners, or aluminum rivet-like connectors which must be ground off to remove. Some of the reasons why nondestructive removal of the dome for reuse elsewhere might be a bit labor intensive.


screw it in

Putting in the rest of the node fasteners (NSF photo courtesy Jerry Marty)



milling around
The last dome beam was installed on 4 January 1973. At left, the dome is fully erected, with panels being installed. The machine parked in the right foreground is one of those Peter Snow Millers (photo from Bob Nyden).


geodesic doom

At right is a closeup view of the dome exterior frame with the panel installation underway. (NSF photo courtesy Jerry Marty)



100% tieoff? 

Meanwhile, the arches were happening too....This view from 1972-73 is looking southwest with the construction camp in the distance. (from the Pole Soul mystery negatives we found in 1977)



no entry

This unique view shows the dome and power plant arch near the end of the 72-73 season. When the dome was designed, NSF didn't know how large the modular sections of the main station structures would be, so the dome design included provisions to remove a portion of the dome wall to get the "vans" inside. This proved unncessary; all of the components for the interior structures were brought in through this entrance. US Navy photo courtesy Billy-Ace Baker


plans office

Here is a construction Jamesway west of the newly completed dome. The emergency exit is visible to the right. US Navy photo, AJ 7/73



gimme shelter
At right, the partially complete power plant and garage arches at the end of the 1972-73 season, boarded up for the winter (this and the next two pictures from Bob Nyden).


arch rivals? 

Another view of the 2 partially completed arches at the end of the season.


no driftiness
At right is a back view of the dome at the end of the station, taken on 25 January, 1973. Caption: "The new geodesic dome at the South Pole Station, Antarctica. This dome will be used to cover and protect most of the buildings at the South Pole." Photographer EA3 D. Nelson.


 

 

hard truth?

At right, early in the 1973-74 season, the back part of Biomed is being assembled along with the biomed arch. NSF photo from Jerry Marty
the view from the construction camp

At left is a much more distant view looking through the arches towards the beginning of the Biomed construction. NSF photo by Rolf Bionert



please use side door

A bit later, the Biomed structure and arch are being completed...based on events of the last few years this clinic is rather famous these days. NSF photo from Jerry Marty

During 1973-74, the Navy (NMCB-71) continued construction on the arches and above-surface structures, while Holmes and Narver (H&N) worked on utilities in the utilidor and elsewhere, as well as the fuel system.


down and dirty

At left, at the other end of the arches, the floor panels in the garage/carpenter shop/gym are being installed. NSF photo from Jerry Marty


cat houseAt right, assembling the carpenter shop/gym building panels. The opening in the side of the garage arch will be the passage to the helium arch. NSF photo from Jerry Marty


this power plant is quiet now
A bit further down the arches, here (left) is the power plant being assembled, the 353 engines are visible through the doors. Caption: "19 Nov 73, View showing van being constructed under arch at South Pole Station, Antarctica, Official U.S. Navy Photograph by PH2 Frank J. Mitchell, USN." photo from Bob Nyden


crates of good stuff
All of the construction cargo had to fit inside of an LC-130...the station structures were designed and built by ATCO (the Alberta Trailer Company, whose camps were later used to build the Alaska Pipeline as well as the permanent runway at Rothera). Some ground floor portions of the buildings such as this one were delivered assembled; the upper floors and interior sections were shipped prefabricated and knocked down. This is another mystery photo from the Pole Souls darkroom archive; EO3 Jim Burke of NMCB-71 is driving the 955.

little boxes
Left, another crate being unloaded. VXE-6 delivered more than 50 crates or modules to Pole. AJ 3/75


frame up

Here is what was going on under the dome. At right, looking from the emergency exit towards the galley, in the foreground is a stack of doors. NSF photo, AJ 1/74


SOS

And at left is the comms building, shown here with the temporary stack from the oil heater inside the first floor. These heaters (and lots of stovepipe) were furnished for construction heat as well as for emergency service if permanent power went down. The heaters were poor substitutes for Preways and fortunately disappeared quickly. Some of the round openings for the stacks are still evident on walls of the station buildings. US Navy photo, AJ 3/75


where to store the trash

A bit later in the 1973-74 season, here's the helium arch being erected. The garage arch has been completed, with the end wall installed. Not in the right place, it was discovered recently. It seems that the new garage and power plant arches were designed to align with the end of the original garage arch; when these were built it was discovered that they didn't line up, one ring had been left off of the original garage arch. So a piece was added from the demo'd helium/cargo arch to make things right. NSF photo (and trivia) from Jerry Marty


no drifts yet

The station from the east, here is the fuel arch. This U.S. Navy photo was taken on 4 February 1974 by PH1 K. Thorneley.


awaiting the contractor
This view (right) of the garage/helium arch end of the station was taken at the very beginning of the 74-75 season, before significant landscaping or construction had started. The radome on top of BIT was moved over from Old Pole a few weeks after this photo was taken. from Bob Nyden


blue room
A unique low aerial view of the new station in the 1974-75 summer. At left, attached to the power plant arch, is the original snow harvesting system, a conveyer belt that was supposed to keep the stainless steel tank in the power plant full of water. Not. NSF photo from Elena Marty



the dome is home

This photo is from the cover of the March/April 1975 Antarctic Journal which included the feature article on what we knew as the "new South Pole Station." You can read the article and see more pictures here as a part of Jeff Kietzmann's "save the dome" web site.